Program Directory

 
Supreme Court of Ohio - 2-20-2019 - Case No. 2018-0379 In re Application of Ohio Edison Co.
 
 
In re Application of Ohio Edison Co., Case No. 2018-0379
Public Utilities Commission of Ohio

ISSUES:
- Can the Public Utilities Commission of Ohio (PUCO) impose a cost cap on an electric power distribution company's energy efficiency and peak demand reduction program?
- Must the PUCO follow rule-making procedures to adopt a cost cap for energy efficiency and peak demand reduction programs?
- Did the PUCO adopt an arbitrary cost cap from the three FirstEnergy power distribution companies operating in northern Ohio?
February 20, 2019